§192.14 Conversion to service subject to this part

Current as of Oct 29, 2026Last amended Mar 24, 2017Official text on eCFR ↗

(a) A steel pipeline previously used in service not subject to this part qualifies for use under this part if the operator prepares and follows a written procedure to carry out the following requirements:

(1) The design, construction, operation, and maintenance history of the pipeline must be reviewed and, where sufficient historical records are not available, appropriate tests must be performed to determine if the pipeline is in a satisfactory condition for safe operation.

(2) The pipeline right-of-way, all aboveground segments of the pipeline, and appropriately selected underground segments must be visually inspected for physical defects and operating conditions which reasonably could be expected to impair the strength or tightness of the pipeline.

(3) All known unsafe defects and conditions must be corrected in accordance with this part.

(4) The pipeline must be tested in accordance with subpart J of this part to substantiate the maximum allowable operating pressure permitted by subpart L of this part.

(b) Each operator must keep for the life of the pipeline a record of the investigations, tests, repairs, replacements, and alterations made under the requirements of paragraph (a) of this section.

(c) An operator converting a pipeline from service not previously covered by this part must notify PHMSA 60 days before the conversion occurs as required by § 191.22 of this chapter.

Source: Amdt. 192-30, 42 FR 60148, Nov. 25, 1977, as amended by Amdt. 192-123, 82 FR 7997, Jan. 23, 2017

Compiled from the Electronic Code of Federal Regulations (eCFR), an editorial compilation and not an official legal edition of the CFR. The official text is the Federal Register and the annual CFR edition. §192.14 on eCFR.

Sections that cite this one

  • §191.22 National Registry of Operators.
  • §192.13 What general requirements apply to pipelines regulated under this part?
  • §192.452 How does this subpart apply to converted pipelines and regulated onshore gathering pipelines?
  • §192.619 Maximum allowable operating pressure: Steel or plastic pipelines.