§192.919 What must be in the baseline assessment plan?

Current as of Oct 29, 2026Last amended Dec 19, 2016Official text on eCFR ↗

An operator must include each of the following elements in its written baseline assessment plan:

(a) Identification of the potential threats to each covered pipeline segment and the information supporting the threat identification. (See § 192.917.);

(b) The methods selected to assess the integrity of the line pipe, including an explanation of why the assessment method was selected to address the identified threats to each covered segment. The integrity assessment method an operator uses must be based on the threats identified to the covered segment. (See § 192.917.) More than one method may be required to address all the threats to the covered pipeline segment;

(c) A schedule for completing the integrity assessment of all covered segments, including risk factors considered in establishing the assessment schedule;

(d) If applicable, a direct assessment plan that meets the requirements of §§ 192.923, and depending on the threat to be addressed, of § 192.925, § 192.927, or § 192.929; and

(e) A procedure to ensure that the baseline assessment is being conducted in a manner that minimizes environmental and safety risks.

Compiled from the Electronic Code of Federal Regulations (eCFR), an editorial compilation and not an official legal edition of the CFR. The official text is the Federal Register and the annual CFR edition. §192.919 on eCFR.

Sections that cite this one

  • §192.911 What are the elements of an integrity management program?
  • §192.941 What is a low stress reassessment?
  • §192.947 What records must an operator keep?